Gordonbush, Scotland

  • Location

    Approximately 12 km north-west of Brora, in Sutherland, Scotland
  • WTG Type

    35 x MM82
  • Total Output

    71.75 MW
  • Electricity production per year for

    60,000 homes
  • Operator

    SSE

On 1st March 2012, the last of a total of 35 turbines was installed at Gordonbush, the biggest UK onshore wind farm of Senvion to date. The project has been a massive challenge for the installation team: All 35 turbines were installed during winter, in the far North of Scotland. The site has been operational since June 2012.