Maida San Floro, Italy

  • Location

    Maida San Floro, Italy
  • WTG Type

    MM92
  • Installations

    32 turbines
  • Total Output

    64 MW
  • Operator

    Enel Green Power SpA

The construction of the park was started in May 2010 and was completed in just over eight months, despite the extreme weather conditions that caused a flood in the area. 7 different storage areas were needed for the construction activities necessary to accommodate all the turbines components, 8 cranes and as well as 8 trucks necessary to carry out all the handling operations. The most important data is certainly the number of people employed: 92 professionals have worked on this wind farm.